Products
Our Production
Road and building equipment
|
for shotcrete
Setting the reception and transportation of hard solutions URTZR-1 with torkret installation SO-50AM
Setting the reception and transportation of hard solutions UPTZHR-1 with the gunning installing SO-50PBN intended for reception, storage, preparation, pneumatic conveying and applying fine-grained concrete mix (sand concrete) on various surfaces (air concreting).
Setting the reception and transportation of hard solutions used in the repair and construction of buildings and structures.
Setting the reception and transportation of hard solutions is a structure consisting of a hopper, spray settings from the bunker and transportation systems, elevator wheel drive with drive mechanism, a water tank and a remote control station.
Benefits of installing the reception and transportation of hard solutions UPTZR-1:
-
a hopper can simultaneously take 2,5 m3 mortar mixture;
-
a hopper is warmed;
-
has a heating system that allows you to work at low temperatures;
-
double elevator wheel allows qualitatively rejuvenate and prepares mortar mixture;
-
adjusts ladles provides a constant flow of mortar mixture into the pump;
-
ability to install any type of mortar;
-
shaker produces sift mortar mixture with removal of retention;
-
dimensions allow the station to transport it without the use of specialized transport.
|
Send request
|
Technical parameters
The main characteristics of the facility admission and transportation of hard solutions |
Pump type |
plunger - diaphragm
pneumatic |
Productivity, m3 / h (min) |
up to 6 |
Pressure on the mixture, bar |
up to 15 |
Feeding height, m |
up to 50 |
Range of feed, m |
up to 120 |
Diameter of the plug mud channel, mm |
50 |
Volume hopper, m3 |
0,15 |
Heated hopper, heater, kW |
3,6 |
Total installed power, kW (max) |
19,5 |
Source of compressed air (not supplied)
|
Capacity, m3 |
from 5 |
Pressure, Bar
|
7 |
Dimensions spray installation |
Length * Width * Height, m |
4,85 * 2,5 * 2,37 |
Weight, kg |
3300 |
Concrete mix for spray installation
|
Concrete mix with aggregate size, mm |
up to 5 |
Mark on the workability
|
from P2 |
Mortar mix for spray installation
|
Mortar mix with aggregate size, mm |
up to 5 |
Mark mobilities |
from Pk2 |
|
|